01 · Key DecisionsDecisions to make
- Capital structure The proportions of equity, project loans, bonds, JV and mezzanine that cover Peak Funding, with a buffer
- Pricing and unit mix The launch price, the price increase plan and the proportion of units to sell first
- Payment terms The booking deposit, contract deposit, down payment and transfer instalments directly determine Peak Equity
- Thai and foreign sales mix Measured against the 49% quota and each buyer group's ability to complete transfer
- Form of construction contract Lump sum or GMP, the scope of risk the contractor bears, and retention
- When to start construction All conditions must be met; it is not enough that the marketing schedule says it is time
02 · Finance · Tax · LegalFinance, tax and legal tasks
Finance
- Close the final feasibility from the BOQ and the monthly model, then take it to the investment committee
- Prepare the term sheet and fundraising documents, including conditions precedent (CP)
- Plan drawdowns by S-curve and set the interest during construction (IDC) policy
- Compare terms from several funding sources, including interest, tenor, covenants and fees
Accounting and tax
- Booking deposits and down payments are contract liabilities; revenue is not yet recognised under TFRS 15
- Borrowing costs related to development are capitalised under TAS 23 during construction
- Sales commission: set a policy on how to recognise it under TFRS 15
- Sales of condominium units are subject to Specific Business Tax (SBT), not VAT, but furniture or goods sold separately may attract 7% VAT, so separate the prices clearly in the contract
Law
- Use the statutory form of sale and purchase agreement (SPA) for condominium units, and check advertising content against the rules of the Office of the Consumer Protection Board (OCPB)
- Choose whether to hold down payments through escrow or a down payment account, in line with the roadmap. Escrow is an option for protecting buyers
- Open the foreign quota register from the first day of sales, and keep evidence of overseas fund remittances for use at transfer
- Sign the construction contract, performance bond and CAR insurance before the NTP
03 · RoadmapRoadmap tasks
P4 Funding
| # | Task | Category | Responsible party | Outcome | Time |
|---|---|---|---|---|---|
| 4.1 | Finalise feasibility summary | Investment budget | Finance/FA | Final feasibility & funding requirement | 2–4 weeks |
| 4.2 | ◆ Investment committee/board approval | Investment budget | Board | Investment & budget approval | Gate |
| 4.3 | Funding structure (equity/bonds/JV) | Finance | Finance team | Term sheet for the selected instruments | 4–8 weeks |
| 4.4 | Fundraising documents (legal/trustee/offering) | Law | Lawyer/finance | Subscription/bond/JV documents, trustee, disclosure | 6–12 weeks |
| 4.5 | ◆ Funding close (funds available) | Finance | Finance team | Drawdown possible / instruments effective | Gate |
| 4.6 | Conditions precedent (CP) all satisfied | Legal/finance | Lawyer/finance | Clear the CP checklist | At closing |
| 4.7 | Drawdown plan & interest capitalisation (IDC) | Investment budget | Finance team | Drawdown by S-curve, IDC policy | At closing |
| 4.8 | Insurance & security framework | Legal/finance | Finance/lawyer | Agree insurance & security strategy | At closing |
P5 Sales preparation
| # | Task | Category | Responsible party | Outcome | Time |
|---|---|---|---|---|---|
| 5.1 | Pricing strategy & unit mix | Investment budget | Sales/Finance | Approved selling prices & unit mix | 3–4 weeks |
| 5.2 | Design payment terms | Finance | Finance/Sales | Down payment & instalment schedule ⚠ affects Peak Equity / cash flow | 2–3 weeks |
| 5.3 | Draft sale and purchase agreement (SPA) | Law | Lawyer | SPA + booking form compliant with the law | 3–4 weeks |
| 5.4 | Set up escrow / down payment custody system | Legal/finance | Lawyer/finance | Escrow agreement or down payment account | 2–3 weeks |
| 5.8 | Appoint sales agents / sales channels | Technical | Sales department | Agent agreements, commission terms | 2–4 weeks |
| 5.9 | Approve advertising in line with the law | Law | Sales/Lawyer | Compliant advertising materials ⚠ rules on real estate advertising content | 1–2 weeks |
| 5.10 | ◆ Presale launch | Technical | Sales department | Public launch, open bookings | Gate |
P6 Pre-construction
| # | Task | Category | Responsible party | Outcome | Time |
|---|---|---|---|---|---|
| 6.1 | Prequalify contractors | Technical | PM/QS | Shortlist of prequalified contractors | 3–6 weeks |
| 6.2 | Tender the main works (BOQ) | Investment budget | QS/PM | Issue tender documents, receive & compare bids | 6–10 weeks |
| 6.3 | ◆ Evaluate contractors & sign contract | Legal/CAPEX | Owner/PM | Construction contract, performance bond, retention | Gate |
| 6.4 | Early procurement (MEP/lifts/FF&E) | Technical | Procurement | POs for long-lead items | Ongoing |
| 6.5 | Construction all risks insurance (CAR) & security | Legal/finance | Finance/lawyer | CAR, liability, performance/advance bond | 2–4 weeks |
| 6.7 | Master programme & construction method | Technical | PM/Contractor | Master programme, S-curve, construction method | 2–3 weeks |
| 6.8 | ◆ Issue notice to proceed (NTP) | Law | Owner/PM | Signed NTP – construction starts | Gate |
Sales gallery, show unit and site preparation works are excluded from the table; include their budget in the Marketing and Pre-Construction budget
04 · MetricsMetrics to watch
| Figure | Reference level from the source document | Notes |
|---|---|---|
| Presale before construction starts | 30–50% according to bank criteria | Below 30%, consider a relaunch or re-price; 50–70% is considered safe |
| LTC | No more than 65–75% | Varies by bank |
| Project loan to construction cost | 60–70% | The remainder comes from Presale and equity |
| Pre-transfer receipts to revenue | Example: 24% | See the effect on Peak Funding on the overview page |
| Cancellation Rate | Above 10% problems begin | Monitor monthly by buyer group |
| Marketing cost | 3–5% of project value | Sales commission is a further 3–7% of sales |
| Presale Cash Coverage | 30% or more | Presale cash / remaining construction cost |
- Needs action
- Threshold / cap
- Target zone
Equity to prepare = Peak Funding - loan drawable at the Peak point + risk buffer
The model already uses pre-transfer receipts to reduce the peak, so this formula does not double count
05 · Decision GateDecision gate
Go: issue the NTP
- EIA and building permit complete
- Investment committee has approved the budget and funding plan
- Funding closed and CPs satisfied
- Presale has reached the funder's threshold
- Construction contract signed within budget, with bond and CAR
- Peak Funding covered, with a buffer
No-Go or postpone
- Tender price exceeds budget and VE cannot yet close the gap
- Presale is below the threshold; must re-price or relaunch
- Funding source is not yet ready to draw, even though the term sheet has been signed
- In the stress case, cash goes negative before transfer day
06 · Common PitfallsCommon pitfalls
- Launching sales before EIA approval risks refunds and loss of credibility
- Cutting the down payment to speed up sales without recalculating Peak Funding
- Counting bookings as firm sales without deducting expected cancellations
- Treating a term sheet as available cash while CPs are still incomplete
- Recording down payments as revenue
- Selling units beyond the foreign quota, or not keeping evidence of fund remittances
- Selling all the best units in the first round at the launch price, leaving the hard-to-sell units for when cash is needed most