Chirayuthchai TraisaengsatheanStrategic Finance for Property Development

DSCR, Covenant and headroom

Calculate DSCR from CFADS, measure headroom in the right direction, set up an internal early-warning system, and request a waiver before a breach

Key takeaways

  • DSCR must be calculated from CFADS, not from profit before interest, and you should know how each agreement defines it.
  • The headroom formula must be reversed depending on the type of Covenant. In the example, a DSCR of 1.42x against a 1.25x threshold gives headroom of 13.6%, while CFADS can fall by 12.0% before a breach.
  • Request a waiver 3–6 months in advance, because once a breach has occurred your bargaining power is much weaker.

What DSCR is based on

DSCR = CFADS ÷ Debt Service

CFADS = EBITDA − tax paid − change in working capital − maintenance CAPEX

Debt service is the scheduled interest plus principal for the period. Some documents define DSCR as profit before interest divided by debt obligations, which is only a rough approximation because profit is not cash. Commonly seen minimum thresholds are 1.20–1.50x.

During the grace period, debt service consists of interest only, so DSCR looks high and then falls once principal repayments begin. Forecast the figures across this turning point before signing.

Projects that sell units to buyers have irregular CFADS, so periodic DSCR explains only so much. Read it together with presale coverage, which is the transfer proceeds from contracts already sold compared with the outstanding debt, and with the release price.

Common financial covenants

CovenantFormulaTypical thresholdFrequency
DSCRCFADS ÷ Debt Service≥1.25xQuarterly
LTVDebt ÷ asset value≤70%Annual
LTCDebt ÷ total cost≤70%By milestone
ICREBITDA ÷ interest≥2.0xQuarterly
Net Debt/EBITDANet debt ÷ EBITDA≤4.0xQuarterly
Current RatioCurrent assets ÷ current liabilities≥1.0xQuarterly
Equity RatioEquity ÷ total assets≥25%Annual
Min. Tangible Net WorthNet equity not below the thresholdPer contractAnnual

Non-Financial Covenants

Must do

  • Submit financial statements and a compliance certificate
  • Maintain insurance policies
  • Pay all taxes in full
  • Comply with the law
  • Allow the bank to inspect
  • Notify significant events

Must not do

  • Incur additional debt beyond the limit
  • Grant security to other creditors
  • Sell significant assets
  • Lend to related parties
  • Pay dividends above the permitted amount
  • Change the core business, merge or restructure

Watch out for change of control, material adverse change and key person clauses, as they are often drafted broadly, and for cross-default, which allows a problem in one facility to spread to others. A group of companies should prepare a table showing which agreements refer to each other.

Calculate headroom in the right direction

Minimum Covenant: headroom = (actual − threshold) ÷ threshold

Maximum (ceiling) Covenant: headroom = (threshold − actual) ÷ threshold

Example

CovenantCriteriaActualHeadroom
DSCR (minimum)1.25x1.42x13.6%
LTV (ceiling)70%55%21.4%
ICR (minimum)2.0x3.2x60.0%
Net debt/EBITDA (ceiling)4.0x2.8x30.0%

Headroom shows the distance from the threshold, but the question that matters for management is how far CFADS can fall.

Allowable CFADS decline = 1 − (1.25 ÷ 1.42) = 12.0%

If CFADS falls by 15%, DSCR drops to 1.21x, which is a breach.

Internal early-warning system

StatusHeadroomAction
SafeMore than 15%Monitor as normal
Watch5–15%Increase reporting frequency
Alert0–5%Open communication with the bank proactively
BreachLess than 0%Immediate crisis management

The monthly Covenant report should include actual figures, headroom, a 3–6 month forecast, scenarios and required actions. The key point is to look forward rather than report what has already passed.

When a breach is near

TypeCharacteristicsSeverity
Technical BreachLate or incomplete document submissionLow
Financial Covenant BreachRatio not metHigh
Payment DefaultFailure to pay when dueCritical
Material Adverse ChangeSignificant deterioration in financial positionVery high
Cross-DefaultDefault to other creditorsVery high

Steps for requesting a waiver

  1. See it 3–6 months ahead from the Covenant forecast
  2. Analyse the cause and identify the size and duration
  3. Prepare a remedial plan specifying the additional equity to inject or the sales to accelerate
  4. Talk to the relationship manager first before any formal documents
  5. Submit a waiver request with figures and the plan
  6. Negotiate the terms, including fees and new Covenants
  7. Sign the waiver letter and then check the effect on other agreements

In exchange, banks commonly ask for a waiver fee of around 0.25–0.75% of the outstanding balance, a margin increase of 0.25–0.50%, additional security, new Covenants, more frequent reporting and restrictions on dividend payments.