Chirayuthchai TraisaengsatheanStrategic Finance for Property Development

Sensitivity and stress test: selling price, cost and sales speed

Test selling price, cost and sales speed using real figures from the model, and learn how to distinguish sensitivity analysis, scenarios and stress tests

Key takeaways

  • Sensitivity changes one variable at a time. A scenario changes several variables together. A stress test asks whether the project survives a severe event.
  • For the same percentage change, selling price affects returns more than cost does, because the revenue base is larger than the construction base.
  • A delay destroys IRR even though total profit barely changes. Always look at Peak Funding alongside it.

Three tools, three questions

ToolsMethodQuestion answered
One-Way SensitivityChange one variable at a timeWhich variable matters most?
Two-Way SensitivityA two-variable table, e.g. price × costWhere is the danger zone?
Tornado ChartRank the impact of every variable in a single chartWhat should management time go to first?
Scenario (Base/Bull/Bear)Change several variables together in a coherent wayWhat is the overall result?
Stress TestAssume a severe event with a low probability of occurringDoes the project survive, and is there enough cash?

Sensitivity from a real model

This table is recalculated from the cash flows in the SARARN SUK model, a hypothetical case study. The model's Base Case has a Project IRR of 15.9%, an Equity IRR of 25.4% and a net profit of THB 224.7 million. Only the stated variable is adjusted; all other assumptions are held constant.

Calculation assumptions: variable expenses of 12.3% of revenue move with revenue; corporate income tax of 20% moves with profit; construction cost is hard cost plus landscape and FF&E, totalling THB 630 million; payment timing and distribution of returns are the same as in the Base Case.

CaseProject IRREquity IRRNet profit (THB m)MOIC
Selling price +10%24.2%35.2%3312.07x
Selling price +5%20.1%30.4%2781.90x
Base Case15.9%25.4%2251.72x
Selling price −5%11.7%20.1%1721.55x
Selling price −10%7.4%14.4%1181.38x
Selling price −15%3.0%8.3%651.21x
Construction cost +5%13.7%22.9%2001.64x
Construction cost +10%11.5%20.4%1741.56x
Construction cost +15%9.4%17.7%1491.48x
Construction cost +25%5.3%12.2%991.32x
Price −5% and cost +5%9.5%17.4%1461.47x
Price −10% and cost +10%3.1%8.6%681.22x

Break-even points of the assumptions

CriteriaSelling price can fall byConstruction cost can rise by
Project IRR falls to the WACC of 10%7.0%13.6%
Equity IRR falls to the required return of 20%5.1%10.7%

A price reduction of only 5.1%, or a construction cost overrun of 10.7%, is enough to bring shareholders' return down to the minimum threshold. This is information that decision-makers need to see.

Sales speed and delays

Revenue and variable expenses are shifted in time as specified, while CAPEX stays unchanged. Total profit barely changes, but IRR and Peak Funding change significantly.

Case (share of receipts in Year 2/Year 3/Year 4)Project IRRPeak Funding (THB m)
Base Case 15/35/5015.9%421
Slower sales 10/25/6513.4%497
Much slower sales 5/20/7512.0%621
All receipts delayed by 1 year8.3%745

In the 1-year delay case, Equity IRR falls from 25.4% to 17.4%. This figure does not yet include the interest from carrying debt for longer, so it is a minimum impact. Peak Funding rises from THB 421 million to THB 745 million, which exceeds the equity and facilities available if they have not been prepared in advance.

Scenarios: a Bear/Base/Bull example

This set of figures is an illustrative example from a sample project, used only to show how to lay out the analysis.

VariableBearBaseBull
Average selling price (THB/sq m)128,000135,000142,000
Construction cost (THB/sq m)44,00040,00038,000
Monthly absorption2.0%3.0%4.0%
Average interest rate7.5%6.5%5.8%
Contract cancellation rate12%8%5%
Total revenue (THB m)2,4802,8003,120
Total cost (THB m)2,3102,1001,990
Gross profit (THB m)1707001,130
Profit on Cost7.4%33.3%56.8%
Project IRR9.8%22.5%34.5%
Equity IRR11.2%31.0%52.0%
Peak Funding (THB m)1,5201,100850

Weighting Bear at 20%, Base at 60% and Bull at 20%, Expected IRR = 20% × 9.8% + 60% × 22.5% + 20% × 34.5% = 22.4%. Weighting does not make the Bear Case go away. If the Bear Case actually occurs, funding of THB 1,520 million must be available.

What a stress test should cover

SituationExample assumptionsReference event
Economic CrisisGDP −5%, selling price −20%, cost +15%1997, 2008
PandemicSales halt for 12 months; tourism halts for 18 months2020–2022
OversupplyAbsorption −40%Competitors launch several projects at the same time
Interest Rate SpikeMLR +3%1997
Construction CrisisCost +25%, delay of 18 monthsSupply Chain 2021–2022
Foreign Buyer StopForeign buyer transactions halt for 12 monthsCapital Control
Natural DisasterTsunami, flood, earthquake2004

A stress test result must answer three questions

  • Does Peak Funding in that situation exceed the available sources of funds?
  • Does the loan remain within its Covenant limits? If not, when would the event of default begin?
  • How much additional equity must the shareholders inject, and do they actually have the money?

Risk mitigation approaches

  • Diversify buyer nationalities; do not rely on a single market
  • Use a fixed-price contract with a financially strong contractor
  • Prepare an equity buffer and contingency of around 5–8% of total cost
  • Maintain relationships with more than one bank
  • Set a Presale threshold before construction starts and before drawing the main loan tranches
  • Prepare a price adjustment plan in advance, together with its effect on the collateral facility