Risk Register and 5×5 Heat Map

Score the likelihood and impact of project risks from 1 to 5, rank them by severity, and place them on a heat map, with risk mitigation approaches.

CalculatorStrategic Financial Management Handbook

Extracted from Real Estate Project Strategic Financial Management Handbook: A Practical Guide · Appendix F Risk Matrix
Example from Appendix F: 10 key risks of a condo project. Scores are hypothetical examples

Heat Map (likelihood × impact)

Vertical axis = likelihood, from 5 almost certain to 1 very unlikely · horizontal axis = impact, from 1 minor to 5 severe

Risk level

    Top 5
    Risk Register
    IDCategoryRiskProbabilityImpactScoreLevelRisk mitigation approaches
    ––
    ––
    ––
    ––
    ––
    ––
    ––
    ––
    ––
    ––

    Results are calculations for learning purposes. The figures entered are hypothetical examples, not real project data.

    How to score

    • Likelihood 1 Very unlikely · 2 Unlikely · 3 Possible · 4 Likely · 5 Almost certain
    • Impact 1 Minor · 2 Low · 3 Moderate · 4 High · 5 Severe
    • Score = likelihood × impact. Levels: ≤ 6 Low · 8–10 Medium · 12–15 High · 16–20 Very high · 25 Critical

    Early warning indicators to track alongside

    KRIGreenYellowRed
    DSCR> 1.40x1.25–1.40x< 1.25x
    Days Cash on Hand> 90 days30–90 days< 30 days
    Presale %Above target80–100% of target< 80% of target